The WIEQ project has a 18 months durability. The timetable described in the following picture :
| 2008 | 2009 | Timeframe | |||||||||||||||||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | ||
| Phase 1. Creation of a transitional network | |||||||||||||||||||
| 1.1. Day of launching | 0,5 Month | ||||||||||||||||||
| 1.2. Definition of a Managament Committee | 0,5 Month | ||||||||||||||||||
| 1.3. Company/signature of the collaboration protocol | 1 Month | ||||||||||||||||||
| Phase 2. Exchange of Information and experience and identification of best practices | |||||||||||||||||||
| 2.1. Selection of best practices | 2 Month | ||||||||||||||||||
| 2.2. Identification of best practices and experiences at regional, national and international level | 7 Month | ||||||||||||||||||
| 2.3. Selection of best practices | 2 Month | ||||||||||||||||||
| 2.4. Elaboration of a guide of best practices | 1 Month | ||||||||||||||||||
| 2.5. Accomplishment of study cases | 1 Month | ||||||||||||||||||
| Phase 3. Diffusion, sensibilization and transference to general polices | |||||||||||||||||||
| 3.1. Desiing of a brand and corporative identy | 1 Month | ||||||||||||||||||
| 3.2. Management of a Website | 3 Month | ||||||||||||||||||
| 3.3. Accomplishment of an international Conference on best practices dissemination | 3 Month | ||||||||||||||||||
| 3.4. Development and elaboration of projec's promotional material | 2 Month | ||||||||||||||||||
| 3.5. Having editorial, announcement or press notes published in the media | 2 Month | ||||||||||||||||||
| Phase 4. Managament, monitoring and evaluation | |||||||||||||||||||
| 4.1. Stoering Committee meetings | Half Yearly | ||||||||||||||||||
| 4.2. Monitoring and evaluation | periodicaly | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | Timeframe |
| 2008 | 2009 | ||||||||||||||||||